Import a plan from Primavera P6

Teamhood imports a Primavera P6 project from the XML file that P6 exports. It cannot read an XER file, so export the project as XML.

A P6 layout saved as a CSV file imports as a table. Its Activity Name column maps to the title. Its Activity ID column maps to the Primavera ID field, as the XML file’s Primavera ID column does, so a later import of either file can match the same items.

A row of P6 field codes such as task_name above the column titles is skipped. Dates that P6 marks with A for actual or * for constrained are read as plain dates.

  1. In P6 Professional, open the project. Teamhood reads only the first project in a file.
  2. Choose File → Export.
  3. Choose Primavera P6 - (XML), then Next.
  4. Clear Export XML file to a compressed file. Teamhood reads an .xml file, not a zip file.
  5. Select Finish.
  1. Select + at the top of the sidebar, then Import.
  2. Drop the .xml file, or select the drop area to pick the file. The file can be up to 10 MB.
  3. On Placement, check Create an item for the project. The project then becomes one item, with its WBS elements and activities under it. The option is on by default while Place under is No parent, and off when you choose an item there.
  4. On Map fields, keep the Primavera ID column mapped. A first import maps it to a new text field named Primavera ID, when your role may create fields. Otherwise the column is ignored. A later import maps it to that field, which lets the import match items.
  5. On Review, select the import button, such as Import 672 items.
  • WBS elements and activities, nested as in P6.
  • Start and Finish, completion, relationships, labor resources and milestones.
  • WBS categories, mapped to the Tags field when the organization has one. Each category is one tag, even when its name holds a comma.
  • Activity status, % complete, planned dates and durations, as columns you can map to fields.

Baselines, calendars, constraints, costs, user-defined fields, activity codes and notebooks are left out. How re-importing a plan works explains which dates and lags the import writes.

Importing the plan again without matching creates its WBS elements and activities a second time. To update them instead, select Update matching items on Map fields.