How what-if planning works
In what-if mode, a planning change is kept as a proposal instead of being saved. A proposal keeps the values you set, such as a new Finish.
Teamhood works out what those values move each time the plan changes, and shows the result over the live plan. None of your proposals reaches your organization until you choose Apply.
What a proposal keeps
Section titled “What a proposal keeps”- A planning change is a change to Start, Finish, Duration (d), Estimate (h), Assignees or a dependency.
- Planning changes also include hours on a schedule: the hours of an item per person per day, reserved time, and marking reserved time tentative or firm.
- A proposal keeps what you set, not what it moved. The dates it moved are worked out again from the live plan every time.
- Your proposals live in this browser tab only. They are not stored anywhere, so closing or reloading the tab asks first.
- One gesture is one step.
⌘ZorCtrl+Zsteps back one gesture, such as one drag or one paste.⌘⇧ZorCtrl+Shift+Zsteps forward again. - Unticking a change in Review shows the plan without it. Every ticked change after it is worked out again.
What you see
Section titled “What you see”- On the Gantt, a moved bar has a dashed amber outline, and a grey dashed outline shows where the bar is now. A moved milestone shows its shift, such as +4d. A proposed dependency is dashed, and a removed one is not drawn.
- On a schedule, the proposed load is the fill. A cell in the load row whose hours the change altered has a dashed amber outline, and hovering it shows the proposed and current hours. The hour cells on an item row show the proposed hours with no outline. A day newly over capacity turns red. A day over capacity in both plans has a soft red wash and red text. A day the change relieves shows no red.
- In a list cell, the current value stays, and an amber chip after it shows the shift, such as +3d. Hovering the cell shows the proposed value. A value with no shift, such as Assignees, shows the proposed value in the chip.
- In item details, the current value is struck through, then the proposed value follows. You can edit it again in either place.
- List order, filters, grouping and rollups use the live values. A proposed change can therefore leave a row where it was.
What the check counts
Section titled “What the check counts”The bar at the bottom counts your changes, the worst deadline impact and the people newly over capacity. The check covers everything you can see in your organization, not only the view on screen. A schedule view that measures load another way says This view measures load differently from the what-if check.
When a colleague edits the same plan
Section titled “When a colleague edits the same plan”- Colleagues’ edits still arrive. Your proposals sit over the live plan, so their edits update what you see.
- When a colleague changes a value that your change also sets, Review shows Changed by someone else to and their value. Apply waits until you choose Overwrite on that line.
- If the colleague changes that value again, the line asks again.
- A colleague who set the same value as yours is not a conflict, because nothing would be overwritten.
What is unavailable
Section titled “What is unavailable”- Edits that are not planning changes are disabled and say Not available in what-if mode. This includes titles, status, comments, time logs, creating or deleting items, and sending in Chat. A few refuse when you use them, and say Turn off what-if mode to make this change.
- Time off and working weeks cannot be changed in the mode, because they set capacity. Time off in the menu of a schedule sweep is disabled and says Not available in what-if mode.
- On a schedule whose estimate is not one of the planning fields above, item hour cells are locked in the mode. Pointing at the item’s bar says Not available in what-if mode, and clicking it opens the item. Changing those hours also changes that field, which a proposal does not hold.
- On the Gantt, Export to PDF and Critical path are disabled until the mode is off. A baseline comparison is hidden until then too.
- An Undo on a message does nothing in the mode. It says Turn off what-if mode to make this change, and the buttons of the Undo panel are disabled. Only
⌘ZorCtrl+Zsteps back, through your proposals.
When you apply
Section titled “When you apply”- Apply turns the mode off, then saves the ticked changes through the normal edits. All of them are one step in the undo history.
- A change you can no longer apply, such as one your role does not allow or one whose item was deleted, shows why in Review. Apply waits until you untick it.
- While Apply saves,
⌘ZorCtrl+Zdoes nothing and says Wait until your changes are saved. - If a change cannot be saved, that change is reverted and a message says so. The other changes stay saved.
Worked example
Section titled “Worked example”Launch is a milestone that waits for Build. You turn on What-if and drag Build a week later on the Gantt.
- Build’s bar moves, and a grey dashed outline shows where Build is now.
- Launch moves too, because it waits for Build, and shows how far it moved.
- The bar at the bottom says that the Launch milestone moves.
- You open Review and untick the change. Build and Launch show where they are now, and nothing was saved.
Behaviours that surprise people
Section titled “Behaviours that surprise people”- A card dropped on a board in the mode snaps back, because the board shows the live plan. When the drop changes a planning field, such as Assignees, Apply still saves it. Any other drop is refused.
- A sign-out turns the mode off without asking, and your proposals are lost.