Try a change before you make it

Turn on What-if, or press W, to try planning changes without saving them. Apply saves them.

The What-if button, a flask icon, is in the toolbar of list, Gantt and schedule views, and in the item details header. The mode covers the whole browser tab, and an amber frame shows it is on.

Change Start, Finish, Duration (d), Estimate (h), Assignees or a dependency. On a schedule, you can also set hours and reserve time. ⌘Z or Ctrl+Z steps back through your proposed changes.

  1. Choose Review in the bar at the bottom.
  2. Under Your changes, untick a change to see the plan without it.
  3. Choose Apply. The ticked changes and what they move are saved, and the mode turns off.

Discard or Discard all turns the mode off at once. The button and W ask first when you have changes.

Review shows Changed by someone else to and the new value. Choose Overwrite to keep your value. Apply waits until you do.