Compare against a baseline
A baseline is a saved copy of the plan a Gantt shows. Capture one, then compare the live plan against it.
Capture a baseline
Section titled “Capture a baseline”Open Tools and choose Capture baseline. The same action sits at the foot of Tools → Baseline. The Gantt starts comparing against the new baseline at once.
Compare against one
Section titled “Compare against one”Open Tools → Baseline and click a baseline in the list. Each bar then shows how its finish compares:
| Bar color | Meaning |
|---|---|
| Red | finishes later than in the baseline |
| Green | finishes earlier than in the baseline |
| Gray | same finish as in the baseline |
| Blue | the baseline does not hold this item |
A thin gray ghost under a bar shows the item’s dates in the baseline. Point at the ghost to read both date ranges.
To stop comparing, choose Clear selection. To rename or delete a baseline, use the menu at the end of its row.
Show baseline dates as columns
Section titled “Show baseline dates as columns”Open the column picker at the end of the table header. Choose Baseline start, Baseline finish, Baseline duration, Start variance or Finish variance.
- The column headers are shorter, such as Δ Finish. Point at a header to read its full name.
- A variance counts calendar days. A positive number means later than the baseline.
- Before you choose a baseline, each cell shows a small icon. Point at it to see where to choose one.
A view too large to capture
Section titled “A view too large to capture”A baseline holds up to 5,000 items. On a larger view, Capture baseline is disabled until you filter the view to fewer items.